ZHU Zhiwei, SHI Huige, TIAN Huimin and et al. Reliability evaluation of on-load tap-changer based on multi-state multi-valued decision diagram[J]. Journal of Light Industry, 2021, 36(4): 118-124. doi: 10.12187/2021.04.015
Citation:
ZHU Zhiwei, SHI Huige, TIAN Huimin and et al. Reliability evaluation of on-load tap-changer based on multi-state multi-valued decision diagram[J]. Journal of Light Industry, 2021, 36(4): 118-124.
doi:
10.12187/2021.04.015
Reliability evaluation of on-load tap-changer based on multi-state multi-valued decision diagram
-
1. School of Electrical Engineering, Zhengzhou University, Zhengzhou 450001, China;
-
2. Nanyang Power Supply Company, He'nan Electric Power Company of State Grid, Zhengzhou 450052, China;
-
3. Electric Power Research Institute, He'nan Electric Power Company of State Grid, Zhengzhou 450052, China
-
Received Date:
2020-07-23
-
Abstract
The Aiming at the problems of large number of bottom events and component polymorphism in the current reliability analysis method of the on-load tap-changer is significantly important for the stability of the transformer and even electrical power system. In this paper, the reliability was evaluated by using the multi-state multi-valued decision diagram (MMDD). First, the reliability evaluation model was built based on the induction and classification of the fault modes of the on-load tap-changer. Second, the of the system reliability is qualitatively andwas quantitatively analyzed by using the multi-state decision graphMMDD. Finally, the reliability of each fault condition of the tap-changer was evaluated under the probability importance of each component. An evaluation Example analysis results showed that the MMDD had the advantages of investigation, deduction, calculation and explanation of the system faults. Further, and the relationship between fault term and system reliability could be obtained.
-
-
References
-
[1]
武文丽,贾俊青,杨德宇,等. 电网故障统计分析及预防措施[J]. 内蒙古电力技术,2020,38(3):94.
-
[2]
郭永基. 电力系统可靠性分析[M]. 北京:清华大学出版社, 2003.
-
[3]
WANG S X,DONG Y C,WU L. Interval overvolt age risk based PV hosting capacity evaluation considering PV and load uncertainties[J]. IEEE Transactions on Smart Grid,2020,11(3):2709.
-
[4]
IRIA J, HELENO M. Optimal sizing and place ment of energy storage systems and on-load tap changer transformers in distribution networks[J]. Applied Energy,2019,250:1147.
-
[5]
VAURIO J K. Importance measures for multi phase missions[J]. Reliability Engineering & System Safety,2011,96(1):230.
-
[6]
胡顺威,周晖,从黎,等. 基于故障树的含电力电子变电站配电网可靠性分析[J]. 电力系统保护与控制,2018,46(21):25.
-
[7]
JIANG J, CHEN R, CHEN M, et al. Dynamic fault prediction of power transformers based on hidden Markov model of dissolved gases analysis[J]. IEEE Transactions on Power Delivery, 2019,34(4):1393.
-
[8]
陈建明,张盼盼. 灰色BP神经网络模型在电力系统短路电流峰值预测中的应用[J]. 轻工学报,2018,33(4):79.
-
[9]
LISNIANSKI A,FRENKEL I. Recent advances in system reliability[M]. London:Springer-Ver lag,2012:113-134.
-
[10]
LI X Y,QI J P, TAMP M. Reliability analysis of the pantograph system based on the T-S fuzzy FTA[J]. Journal of Safety and Environment, 2018,18(1):33.
-
[11]
SHRESTHA A,XING L D. A logarithmic binary decision diagram-based method for multistate system analysis[J]. IEEE Transactions on Reliability,2008,57(4):595.
-
[12]
戴胜华,谢旭旭. 基于改进型AHP与证据理论的应答器系统风险评估[J]. 安全与环境学报,2019,19(1):49.
-
[13]
王有元,袁园,陈伟根,等. 变压器故障发生概率的多特征参量综合评估方法[J]. 仪器仪表学报,2011,32(8):1697.
-
[14]
王宁,胡大伟. 基于多态多值决策图的多态故障树重要度计算方法[J]. 计算机集成制造系统,2015,21(5):1301.
-
[15]
AMARI S V,XING L D,SHRESTHA A,et al. Performability analysis of multistate computing systems using multivalued decision diagrams[J]. IEEE Transactions on Computers,2010,59(10):1419.
-