Monte-Carlo simulation on schedule risk in complex construction project using Bayesian networks
-
Received Date:
2011-11-10
Available Online:
2012-05-15
-
Abstract
Based on the analysis of the risk characteristics of complex projects,Monte-Carlo simulation on schedule risk using Bayesian networks was introduced and schedule risk model was built.An power project as an example is simulated and analyzed.The results showed that the reverse retrospective study can find affect extent of the risk factors related to complex projects,and targeted control methods can be adopted.
-
-